Thermoplastic Lining

McDonalds Long Sutton

Employed by McDonalds Long Sutton Restaurant to resurface overflow car park. Re-engineered existing levels to provide sufficient gradient, installed ACO drainage system connecting into existing drains. Re-graded existing sub-base to reduce cart to tip and relayed new macadam binder course and stone mastic asphalt surface course. Work completed within 2 weeks taking out and relaying 140m kerb 32m ACO and regarding and surfacing over 750m2.

McDonalds Nuneaton

Frank Tucker Ltd were awarded the contract to re-surface the existing car park and new dual drive thru lane at McDonald’s restaurant in Nuneaton. The main contractor Mark James Contract Building Services have used our services for the last 2-3 years.

As with all McDonald’s contracts the deadlines are very tight and all parties concerned worked well together to produce an excellent end product.

The general scope of work was:

Carryout necessary road planning to achieve design falls (Day 1 Visit 1)
Provide and lay regulating material to achieve design falls (Day 1 Visit 2)
Provide and lay binder course to new DT lane and various car park extensions (Day 1 Visit 1)
Provide and lay 35mm thickness 10mm SMA to entire car park (Day 1 Visit 2)
Installation of associated thermoplastic lining.

All work was carried out over 2 visits both consisting of 1 day and all work was carried out in conjunction with numerous trades completing extensive alteration works to the building so liason with other trades was vital. In total some 200t of material was laid in difficult circumstances and all to the ultimate satisfaction of our client.