Stone Mastic Asphalt Surface

McDonalds Long Sutton

Employed by McDonalds Long Sutton Restaurant to resurface overflow car park. Re-engineered existing levels to provide sufficient gradient, installed ACO drainage system connecting into existing drains. Re-graded existing sub-base to reduce cart to tip and relayed new macadam binder course and stone mastic asphalt surface course. Work completed within 2 weeks taking out and relaying 140m kerb 32m ACO and regarding and surfacing over 750m2.

Aldi Bramley

Frank Tucker Ltd were awarded the contract to provide and lay base, binder and stone mastic asphalt surface course to the newly constructed Aldi store car park in Bramley.

The car park was prepared by others and a tight 3 day program was allowed to complete works for the hand over.

The general scope of works was:

Provide and lay 300t 28mm base
Provide and lay 270t 20mm binder
Provide and lay 250t 10mm SMA

All works were completed early October 2013 to the satisfaction of the client.