Aldi Bramley

Frank Tucker Ltd were awarded the contract to provide and lay base, binder and stone mastic asphalt surface course to the newly constructed Aldi store car park in Bramley.

The car park was prepared by others and a tight 3 day program was allowed to complete works for the hand over.

The general scope of works was:

  • Provide and lay 300t 28mm base
  • Provide and lay 270t 20mm binder
  • Provide and lay 250t 10mm SMA

All works were completed early October 2013 to the satisfaction of the client.